ACT AppealIndonesia - ASID82Capacity Building & Disaster Risk Reduction / ManagementGeneva,
22 July 2008
Appeal Target:
US$ 1,398,910 Since
a devastating earthquake struck Central Java and Yogyakarta provinces
in May 2006, members of the global alliance Action by Churches Together
(ACT) International, Church World Service (CWS), Yakkum Emergency
Unit (YEU), and Yayasan Tanggul Bencana di Indonesia (YTBI) in Indonesia
have been providing relief and rehabilitation assistance to people
in affected villages through ACT appeal programme (ASID 61), which
closed at the end of November 2007. While assistance provided to
date has saved lives and enabled many people to advance on the long
road to full recovery, the external ACT evaluation of the ASID61 programme
and the members’ own re-assessment of the situation in the affected
communities, revealed gaps in assistance in some geographical areas,
sectors and to some vulnerable affected communities. This region faces
a high level of environmental hazards, including floods, earthquakes,
volcanic eruptions and drought, leaving many people’s livelihoods
in the earthquake-affected areas uncertain or highly vulnerable. Complementary
assistance is needed, with a focus on Disaster Risk Reduction (DRR),
to ensure the sustainability of livelihood recovery, and to strengthen
the community preparedness and longer-term resilience. ACT members
have identified further needs in some of the villages for adequate
water supplies, sanitation and hygiene promotion. Also identified
as areas in need of support are: the further development and strengthening
of community-based organizations; health posts providing village-level
health services, livelihood activities and disaster preparedness;
and the involvement of local schools, teachers, children and government
to strengthen local networks for better community-based preparedness
and management of disasters. Additionally, it has been proposed that
work needs to continue in promoting the rights of physically disabled,
men and women, through advocacy and community-awareness campaigns
and activities. Proposals
for response have now been received by the ACT Coordinating Office
and a follow-on appeal is hereby submitted for your consideration. Project
Completion Dates: CWSI
- 31 July 2009 YEU
- 31 July 2009 YTBI
- 31 July 2009 Reporting
schedule: CWSI YEU YTBI Interim
narrative & financial 28
February 2009 28
February 2009 28
February 2009 Final
narrative & financial 30
September 2009 30
September 2009 30
September 2009 Audit 31
October 2009 31
October 2009 31
October 2009 CWSI YEU YTBI Total Target US$ Appeal
Targets 650,559 443,385 304,966 1,398,910 Less:
Pledges/Contr Recd 0 0 0 0 Balance
Requested from ACT Alliance 650,559 443,385 304,966 1,398,910 Note:
Balances from ASID61 have yet to be verified - audit reports are
still awaited at the CO. Once the balances have been verified,
donors will be notified of their unspent funds and contacted individually
to approve transfer to this follow-on appeal or to redirect further. Signed
by: Robert White
|
||||||||||||||||||||||||||||||||||||||||||||||||||||