![]() |
![]() |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
ACT AppealPakistan - ASPK61, REVISION 2Earthquake Recovery & RehabilitationGeneva,
17 September 2008
Appeal Target:
US$ 16,964,231 Total cover:
US$15,696,095 No further
funding requested due to limited implementation period remaining. On
8 October 2005, an earthquake registering a magnitude of 7.6 on the
Richter scale caused havoc in an area of 30,000 sq/km in the NWFP
province of Pakistan and in parts of Pakistan-administered Kashmir.
It was the deadliest earthquake in the recent history of the sub-continent
resulting in between 73,000 and 86,000 deaths. The earthquake affected
the lives and livelihoods of an estimated 3 million people. A first
ACT appeal (ASSA51) was launched for both Indian and Pakistani areas
of Kashmir, and followed by this rehabilitation phase appeal which
was first launched on 10 April 2006, and revised for the first time
on 06 October 2006. Please
find attached the second and final revision of the ASPK61 appeal for
ACT member Church World Service (CWS)- Pakistan/Afghanistan’s rehabilitation
programme, with an implementation period of two years and eight months,
to close on 31 December 2008. This final revised version of the appeal
also includes a Diakonie Katastrophenhilfe (DKH) rehabilitation programme
as approved for inclusion and shared earlier with the alliance in
September 2007. DKH have been implementing both directly and through
an established local partner with an implementation period ending
30 November 2008. Please note no funding has been requested for DKH
as their full budget of US$ 1,620,000 is covered by DKH themselves. The
most recent revision of CWS’s programme took place in March 2008 in
close coordination and communication with the ACT Coordinating Office
and the larger funding contributors towards this appeal. At the same
time an accompanying extension of their implementation period was
approved for an additional 9 months to 30 November 2008. While the
changes in CWS’s section of the appeal were agreed in principle with
the ACT Coordinating Office and communicated to appeal supporters,
this formal approval and issue of the revision as per normal ACT procedures
was unusually delayed due to competing emergencies work of the Asia,
Pacific and Europe desk of the ACT Coordinating Office. The reasons
for revision as explained at that time are as follows:
CWS
have reported that the programme targets are on track and they are
hoping to complete all planned activities in couple of months, except
for the School Safety Programme. In the School Safety Programme,
40 schools were targeted for retrofitting. However, the government
(ERRA) did not grant CWS the approval to proceed with the concept
of retrofitting due to lack of specific technical expertise. However,
approval was given to work on school reconstruction, which
then required more funds. Please note that with this change is plans,
the budget earmarked for school safety is only sufficient to cover
6 schools and this is where CWS have focused time and efforts. Reconstruction
of all six schools is in progress. A further one month extension of
the implementation period has been requested and approved for completion
of this work by 31
December 2008. A
final ACT evaluation of the programmes within this appeal will be
conducted. Please
see the reporting schedule that follows for deadlines for full ACT
reporting on both the CWS and DKH programmes in the appeal. Project
Completion Date: CWS
P/A - 31 December 2008 DKH
- 30 November 2008 Reporting
schedule: Reports
due ACT CO Interim narrative & financial reports Final narrative & financial reports Audit CWS P/A 1st 31
Oct 2006 28
February 2009 31
March 2009 2nd 30
April 2007 3rd 31
Oct 2007 4th 30
April 2008 DKH N/A 31
January 2009 28
February 2009 Summary of Appeal Target, Pledges/Contributions Received and Balance
Requested: CWS / NCA DKH ACT Co-ordination Evaluation Total Target US$ Total
Appeal Target/s 15,229,231 1,620,000 35,000 80,000 16,964,231 Less:
Pledges/Contr Recd 13,967,316 1,620,000 28,772 80,008 15,696,096 Balance
Requested from ACT Alliance 1,261,915 0 6,228 +
8 1,268,135 Note:
Appeal ASSA51 has been completed. Reports are awaited
and transfer of any balance to ASPK61 will be requested. Signed
by: John Nduna
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||